Construction Update!

Construction Update!

Due to COVID related events the substantially complete date for construction has been moved into September.

 
Millwork installation and flooring is ongoing in the hospital. Plastic wall protection has been installed in the patient rooms and continues to the next area. Ceramic tile flooring is underway in the dining area. The exterior ceiling is complete at the ER canopy and starting at the main entrance canopy.
 
The east main entrance driveway is complete. The walls are being primed in the imaging area.
 
Mechanical work continues in the mechanical building. The exterior canopies have been delivered to the site and installation will start Monday.
 
The Medical Office Building is getting the first coat of paint. Millwork is wrapping up. All flooring is complete except for carpet.
 